Project for the design, manufacture/fabrication, inspection, testing and Supply, Skid Design, Fabrication, Assembly and Test. Exxel Objects was responsible for the design, procurement, quality of materials, and compliance with the requirements of the applicable specifications, data sheets, standards, codes and regulations as stated.
Exxel Objects provided the electrical, instrumentation/control, mechanical and structural items to complete the commissioning and start -up of Fire Water Pump
Designed and supplied 2 Air Coolers to Erbil , Kurdistan:
The design is to supply the Structure Steel , walkway and ladders ahead of the coolers and will be shipped in an open top 40 ft container
Each cooler is designed of 4 Bundles that each will be shipped in an open top 40 ft container
Total shipment is 10 x 40 ft open top containers.
Directly from shipping containers to on site location at the steel structure
The EPC project including Scada Control Room, 59 RTUs for Gas Services, Interlocking Valves, Scrapers Stations andGas Terminal, Field Instrumentations,
Photovoltaic System and UPS, Telecommunication System, Shelters for RTU and Leak Detection System