Solar

1. Al-Husainiyah Power Generation Project, Jordan:

a. The project was a 50 MW PV Solar Project built on 1,300,000 square meters, located in the town of Husainyah, about 15 Km north of Ma'an.
b. JA Solar PV Poly Crystalline-P72-330Wp panels were used.
c. ABB PVS980-58-2000KVA-K inverters were used
d. Single Axis Trackers
e. The Scope was developing and construction of the project on behalf of the owner(s) (AMEA Power-Dubai and Philadelphia Solar- Jordan).

2. Phoenix Power 1 s.a.e - Within the Benban (Aswan) complex, Egypt

a. Design Vetting and permanent site supervision
b. 50 MW PV Solar Project using Canadian Solar PV Modules and Sun-grow Inverters.
c. The project was completed on schedule

3. DEWA Phase III 800 MW PV Solar Project - Dubai - UAE:

a. The role of ILF Consulting Engineers was the Implementation Consultant for the Emirates Solar Power Company L.L.C (SHUAA) of the 800 MW PV Solar Project.
b. Canadian Solar PV Nodules were used and ABB Inverters.

4. The Shams Ma'an Project in Ma'an - Jordan. This project was one of the first PV Solar Projects in Jordan:

a. The EPC contractor was First Solar using their own "thin-film" PV Modules technology to build a 52.5 MW Solar Power Plant.
b. It was completed, in 2016, the facility will supply an estimated 160-million-kilowatt hours (kWh) of electricity per year, which is equivalent to approximately one percent of Jordan's annual energy output