Oil Immersed Power Transformer, 80 MVA – Hitachi Energy

project details
Name:

2 x 80 MVA Transformers

Industry:

Data Center

Customer:

Confidential – Data Center Developer

Location:

Ireland

Value:

Confidential 

Duration:

11 Months

Scope of Services

Exxel Objects was contracted directly by the developer on an EPCC (Engineer, Procure, Construct,Commission) basis for the complete design, engineering, supply, logistics, installation, assembly,commissioning and handover of two 50 MVA transformers on the customers energy center.

Given the critical path nature of the scope, Exxel Objects was able to procure and install these transformers within 10 months. We achieved this through our relationships with a number of our partner transformer manufacturers where we purchased a number of manufacturing slots on behalf of our customers to enable them and us to guarantee shorter lead times than our competitors. It also involved proactive management of the assembly and commissioning stages to ensure the works were coordinated with all other site activities and carried out safely.

Project Delivered on Time
Project Delivered on Budget
No LTI

Data Centers

Project Gallery

get in touch

Let's Discuss Your Project Together

Architecture and construction are two of the most important aspects of any building project. Whether it’s a residential home or a commercial structure.

Start Your Project Today

Powering Critical Projects with Speed & Reliability

Share:
Social